รายละเอียดงาน- Understand project specification and construction process color coding, NDE ratio, painting SPEC, welding method, ITP, material specification with welding process
- Responsibilities include record keeping, all documents such as specification procedures, inspection schedule and records, surveillance report, inspection release notice and quality records book with numbering system according to project filing procedure. Handling of all inspector documents. Controlling all records documents
- Finish History sheet after welding and NDE completed within 10 days.
Hydro test package preparation must complete one month before hydro test start and NDE complete 1 week before hydro test.
To be finish spools or structure member inspection with Document reporting due to schedule must be not lately over 10% of job by 1 Month.